We manufacturing transformer and substation equipment supports columns from 110-220-500KV. These are indispensable products to support equipment in 110-500KV substations. Columns can be made of U, H, L, I steel depending on the design. Materials for making columns are of clear origin. Cylindrical products are tested and strictly controlled in terms of structure as well as welds after completing product manufacturing.
Cùng với sự phát triển của đất nước, chúng tôi còn chế tạo- sản xuất rất nhiều sản phẩm cơ khí phi tiêu chuẩn dựa trên bản vẽ thiết kế của khách hàng. Với phương châm phục vụ khách hàng hết sức mình chúng tôi luôn cố gắng đáp ứng càng nhiều các yêu cầu […]
Steel pole products are products used for power transmission and distribution, arranged outdoors. Including support poles, anchor poles, over poles with voltage levels from 110-500KV. All steel towers are checked and controlled under a closed process from material checking, implementation, modeling and trial installation special software – actual trial installation after production. This process ensures […]
Hot-dip galvanizing is a cost-effective, long-lasting and effective method in the industry nowadays. Hot dip galvanizing is a method for protecting materials against corrosion by the most optimal natural conditions , outstanding service life with zinc coating and extremely low maintenance costs. All products manufactured at Ngai Cau company are hot-dip galvanized, ensuring enough thickness […]
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020