Welding
Sơn La, Viet Nam
HBRE
2017 -2020
Construction Mechinery Joint Stock Company No. 26 (Coma 26) is the construction unit of 220KV Loc Ninh - Binh Long 2 directly ordering steel poles of Ngai Cau. - 220kV Loc Ninh - Binh Long 2 Power Line project…
The project was started from February 2019 including Solar Park 1 and Solar Park 2 solar power plants built on an area of 118 hectares in Hamlet 3, Binh Hoa Nam Commune, Duc Hue District, Long An Province. Syouei Alliance (Japan) – TWT….
Phase 1 of Xuan Thien Ea Sup Solar Power Plant Project has nearly two million solar panels, with a capacity of 600 MWac/831 MWp, a 500 kV/1,200 MVA substation and 22.2 km of 500kV transmission lines, with an investment of nearly 20,000 billion VND, electric…
The largest 450MW Trung Nam Thuan Nam solar power project in the country and Southeast Asia with the first 500kV transmission and substation system invested by the private sector. Project of 500kV substation and 220/500kV transmission line combined with Solar Power Plant…
- HA NOI ASSEMBLE ELECTRICITY JOINT STOCK COMPANY is the construction unit of the project: Output 110kV line after 220kV Lang Son substation directly order steel poles, anchor bolts, Earthing of Ngai Cau. - The Output 110kV project after the Lang Son 220kV substation belongs to…
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020
Vietnam's fourth and largest Wind farm ever built in Vietnam, using most state-of the-art turbines and systems by GE
Total investment: 0.56 billion USD engineering, procurement, supply, construction and commissioning contract.
Total capacity: 280 MW
Client: HBRE
Location: Ea H’leo, Dak Lak, Viet Nam
Start date: 2017
Completion date: 2020